It's been a slow week at our house construction site so we've taken care of ordering things and Roy's worked on the storage shed. The well man came to move the tank from the blocks it was on to its permanent slab home! Roy planted the two bay leaf plants we took with us from… Continue reading 01.16.2015 Very little construction update! Roy’s birthday and other updates…
Category: Amite house construction
01.09.15 Septic Tank Day!
1/9/2015 I woke up this morning to equipment digging up ground. ABC Well and Sewage arrived to put in our septic tank! We moved Dora forward several feet but not out to the road like before. Just enough to get her rear end out of their way! Before he put the top of the tank… Continue reading 01.09.15 Septic Tank Day!
01.07.15 Construction update and sweets!
1/6/15 An army of men showed up today and what a wonderful site that was! Our contractor Ronnie was here supervising everything. The digging crew was here bright and early preparing the dirt for the slab. They worked hard and got the job done by noon. Here's pictures of them making progress throughout the morning.… Continue reading 01.07.15 Construction update and sweets!
01.05.2015 Update on house construction
We purchased all the kitchen appliances yesterday, all matching Frigidaire, to be delivered when the time is right! That will be a happy day! The storage shed parts will be delivered tomorrow and as always Roy is terribly prepared for this project. Yesterday we bought 12 concrete blocks and 8 -4x4 treated posts for the… Continue reading 01.05.2015 Update on house construction